Create Manpower Entries

Background

The Manpower section lets you track people on site who performed work on the project that day. It allows for the collection of data, including companies on site, number of workers, hours worked, cost codes associated with the work.

You can configure the Manpower section so that the values of Hours and workers on a copied manpower entry are automatically set to zero. See Configure Daily Log Advanced Settings.
Note: If the Set Hours and Workers values to 0 on copy setting is not enabled in the Daily Log Settings > Manpower screen, the copied manpower entry will retain the number of hours and workers from the previous entry.

Things to Consider

  • Required User Permissions:

    • To create entries: 'Standard' or 'Admin' level permissions on the project's Daily Log tool.

    • To create pending entries as a collaborator: 'Read Only' or 'Standard' permissions to the project's Daily Log tool with the 'Collaborator Entry Only' granular permission enabled on your permissions template.

  • Additional Information:

Steps

  1. Navigate to the project's Daily Log tool.

  2. Scroll to the Manpower section.
    You can also use the left navigation menu to quickly navigate to the Manpower section.

  3. To create an entry, add information to the fields.
    You can configure specific fields in the Manpower log as required, optional, or hidden in the company level Admin tool.

    Note: Click the caret icon > to expand and v to collapse the field names and their descriptions below.

    Manpower - Field Names and Descriptions

    • Company: Select the company or individual performing the work from the dropdown menu.
      Note: Companies and users must first be added to the project's Directory tool so they can be selected in this dropdown menu . See Add a Company to the Project Directory. In addition, a user must be marked as an employee of your company to appear in this dropdown menu. See Add Someone as an Employee of Your Company.

    • Workers: Enter the number of workers from the selected company on the job for the day.

    • Hours: Enter the total number of hours each worker from the selected company performed on the job that day. If workers from the same company worked different hours, Procore recommends creating a separate entry.

    • Total Hours: A read-only field that displays the product of workers and hours. For example, 3 (Workers) x 7 (Hours) = 21 (Man Hours).

    • Location: Select the project location from the dropdown menu.
      Note: If your project settings permit, you can also create and select a new location from this tool. See How do I add a multi-tiered location to an item?

    • Trade: Select the trade associated with the entry from the dropdown menu. You can only select from the trades already added to the project. See Add a Custom Trade.
      Note: This field is not enabled by default, so it may not be available on your entry. Company Admins can add the field through a configurable fieldset applied to the project.

    • Cost Code: Select the cost code associated with the entry from the dropdown menu .
      Note: This field is not enabled by default, so it may not be available on your entry. Company Admins can add the field through a configurable fieldset applied to the project.

    • Comments: Enter any comments or additional information that further describes the entry (if required).

    • Attachments: Attach any additional files to the entry. To attach files, do one of the following:

      • Click Attach File(s) and then drag-and-drop a file from your computer to the Drag and Drop your File(s) area.

      • Click Upload Files to select a file from your computer.

  4. Click Create.
    The log entry is created or added.

Next Step

See Also