Configure Flat Rate Columns
Beta
Company Administrators can enable the Resource Management: Rate Tables - Company & Project Rate Management beta in Procore Explore. (US 2 | UK)
Company Administrators can enable the Resource Management: Rate Tables - Company & Project Rate Management beta in Procore Explore. (US 2 | UK)
To build a rate table, you must first define its columns. Rate columns categorize your rates by type (labor or equipment) and financial purpose: cost rates represent the internal expense incurred by using a resource, while billable rates represent the amount charged to a client.
Additionally, the Allow Project Overrides setting controls flexibility. If enabled, projects can customize the rates assigned from the company level. If disabled, projects must use the rates as-is. Typically, you will keep overrides disabled for fixed internal costs, but enable them for billable rates so projects can adjust pricing to match specific client contracts.
After you create a rate, the Resource Category cannot be edited.
Columns cannot be deleted. However, they can be edited and repurposed.
Navigate to the company's Rates tool.
Click the configure settings
icon.
Click Create and select Flat Rate.
Enter the flat rate column information.
Set Overrides and Privacy.
Allow Project Overrides. Mark the checkbox to allow project rate admins to override the value for their specific project.
Save the column.
Click Save to save changes made to the column.
Click Save as New Column to create a new column.
To edit columns, select the column and update the information. Then click Save.