Add Quantities to a Timesheet (iOS)

Background

Production quantities are a measurable amount of work on a construction project. For example, cubic yards of concrete, number of light fixtures, or linear feet of piping. In Procore, there are two types of production quantities:

  • Budgeted production quantities refers to the measurable amount a team plans to install on a project.

  • Installed production quantities refers to the actual amount installed on a project by a point in time.

After installed production quantities have been entered in a timesheet, they can be tracked against the imported budgeted production quantities using the Production Quantity Report.

Things to Consider

Prerequisites

Steps

After you fill out your timesheet, perform the following actions before you submit:

  1. Tap Submit.

  2. Tap Submit and Add Quantities.
    2018-07-10_10-21-27.png

  3. If prompted, click Add Line.

  4. Tap Units Installed Today and enter the quantity installed.

  5. Optional: Enter any notes.

  6. Click Submit.