Elevate a Coordination Issue to an RFI
During project coordination, construction issues are tracked as coordination issues to streamline collaboration and model refinement. However, if an issue requires a formal response, it can be elevated to a Request for Information (RFI). This ensures official tracking and documentation for clarity that could impact cost, schedule, or scope.
The issue's status automatically updates based on the RFI's progress:
Elevated: The status changes to Elevated as soon as the issue is linked to an RFI. It will also revert to Elevated if the RFI is reopened without an 'Official' response.
Released: The status changes to Released once an 'Official' response is added to the RFI. It remains Released even if the RFI is reopened, provided the 'Official' response is logged.
Things to Consider
Additional Information:
You can alternatively elevate issues to RFIs from the Procore BIM Plugin. See Elevate a Coordination Issue to an RFI from the Procore BIM Plugin.
Steps
Follow these steps to elevate an issue to a new or existing RFI.
Navigate to the project's Coordination Issues tool.
Click the Issue link to open it in the Issue [#] panel.
Elevate to RFI
Click the
icon and choose Elevate to RFI > Elevate to New RFI. In the New RFI panel, complete the required fields and add optional information as needed.
Click Create Draft.
A confirmation banner appears with a link to the draft. An 'Admin' on the RFIs tool must set the RFI's status to Open to start the workflow. You cannot close or re-elevate the original issue until the new RFI is closed.
Elevate to Existing RFI
Click the
icon and choose Elevate to RFI > Elevate to Existing RFI. In the Select an RFI panel, search for the RFI by number or subject.
Click the desired RFI in the list.
Click Elevate to this RFI.
Next Steps
See Also