End a Resource Assignment
Background
Resource assignments allow you to manage your resources by assigning them to projects. You can end a resource assignment by updating the end date the current date.
Things to Consider
Steps
You can end resource assignments from the following places in Resource Planning:
End an Assignment from the Assignments Boards
Navigate to the Company level Resource Planning tool.
Click Assignments and select Boards.
Locate the assignment you want to edit.
Drag and drop the assignment from the project to the 'resource bench'. See What is the 'resource bench' in Resource Planning?
Note: The assignment end date updates to the present date.
OR
Locate the assignment you want to end and hover over the assignment. Next, click the Gantt
icon.Click Edit Total Assignment.
Enter the new End Date.
Choose an option to save the assignment:
Click Save.
Select the caret
icon and select Save and Alert to save the assignment and send an assignment alert to the assignee.Optional: Update the 'Subject'.
Optional: Update the 'Alert Content'.
Select when to send the alert:
Send Now. Select this to send the alert immediately, then click Send.
Note: This will send the alert immediately based on the default or project assignment alert settings.Schedule. Move the toggle to the ON position to schedule the alert to be sent in the future.
Note: You can edit or send the scheduled alert at a later time.Select the Date and Time to send the alert.
Click Save.
Save Draft. Select this to save the alert as a draft. Then click Save.
End an Assignment from the Assignments Gantt
Navigate to the Company level Resource Planning tool.
Click Assignments and select Gantt.
Select the Project Assignment Bar beside the person whose assignment you wish to change.
Click the colored bar of the days you want to edit.
Select Edit Total Assignment to edit the entire assignment.
Enter the new End Date.
Choose an option to save the assignment:
Click Save.
Select the caret
icon and select Save and Alert to save the assignment and send an assignment alert to the assignee.Optional: Update the 'Subject'.
Optional: Update the 'Alert Content'.
Select when to send the alert:
Send Now. Select this to send the alert immediately, then click Send.
Note: This will send the alert immediately based on the default or project assignment alert settings.Schedule. Move the toggle to the ON position to schedule the alert to be sent in the future.
Note: You can edit or send the scheduled alert at a later time.Select the Date and Time to send the alert.
Click Save.
Save Draft. Select this to save the alert as a draft. Then click Save.
End an Assignment from the Assignment Gantt (Beta)
In Beta
This feature is in beta and available for customers using the Resource Planning tool.
Navigate to the Company level Resource Planning tool.
Click Assignments and select Gantt (Beta).
Locate the assignment you want to end.
Hover over the end date of the assignment bar until you see the arrows.
Click the arrows and and move the length of the bar to the new end date using a drag-and-drop operation.
Tip
Click the undo
icon to undo an action. Click the redo
icon redo a previously undone action.